The line planning calendar

By Published Editorial policy

The line planning calendar is the sequence of dated milestones that takes a season’s line from strategy to a locked line and a released line sheet, worked backwards from the date the product has to be in store or ship. It is the line planning process expressed as dates: when the strategy is signed, when each line review is held, when the line locks, when the line sheet reaches accounts, when purchase orders are placed — and how far ahead of the floor date each of those has to happen.

This page is about timing. What line planning decides, who owns each decision and the arithmetic that turns a budget into an option count are in what is line planning; how a review is run, in how to run a line review; what a lock commits and how to change a locked line, in locking the line; and how many drops a season should have, in planning drops on the line board. Each of those assumes a calendar. This page lays one out.

Below: the fourteen milestones in order and what each decides, needs and releases; how to schedule them backwards from the end date in eight steps; an illustrative dated calendar for a Fall 2028 first delivery, checked week by week; where the four locks sit on it; how two or three seasons run in flight at once; the critical-path dependencies; drops and channels; how the calendar changes in apparel, footwear, beauty, home and furniture, toys and outdoor and sporting goods; the failures that recur; and how to keep a calendar that people actually plan their weeks from.

The short version
A line planning calendar fixes the end date first — the floor date, the ship window or the retail partner’s reset — and works backwards through shipping, production, fabric and trim, the buy, the prebook and market week, the line sheet, the lock, the final review, costing, development, the first review, the architecture, concept, hindsight and the season strategy. In the illustrative wholesale apparel calendar on this page, that puts the strategy 60 weeks before the floor, the lock 34 weeks before it and purchase orders 22 weeks before it. Those durations are assumptions for the example, not benchmarks. The calendar fails in three predictable ways: the lock moves and the ship date does not, reviews are scheduled before costs are known, and line sheets go out before the line is locked.
Definition — Line planning calendar
The dated schedule of a season’s line planning milestones — strategy, hindsight, concept, architecture, line reviews, development, costing, lock, line sheet, market, buy, production and ship — set backwards from the in-store or ship date so that each milestone has a latest date and a named owner.
Latest date for a milestone = the date of the milestone after it − the lead time between them, starting from the floor or ship date and working back
Used by: Merchandising and planning own it; design, product development, sourcing, sales and logistics plan their own weeks from it
Related: Line planning, line plan, line review, line lock, line sheet, market week, prebook, critical path, floor date, delivery drop

Why a line plan needs a calendar

A line plan says what the season contains. It does not say when any of it has to be decided, and most of what goes wrong in a season goes wrong on a date rather than in a number. The option count was right, but it was signed after the fabric for it had to be booked. The margin was right, but it was checked on target costs because the quotes arrived the week after the final review. The line sheet was right, but it went to accounts before the line was locked, so every later change became a correction.

The calendar is what prevents those. It gives every milestone a latest date, works out what has to exist before that date, and tells the teams downstream when their own work can start. A sourcing team that knows the line locks on a given Monday can line up sample capacity for that week; a sales team that knows when the line sheet releases can book appointments around it; a planning team that knows when the prebook closes can schedule the buy.

Two kinds of date. A calendar contains dates the business controls and dates it does not. The floor date is usually fixed by the delivery calendar the business has promised its stores or its accounts. The market week is fixed by the trade calendar or by key accounts, and a brand rarely moves it. A retail partner’s reset date is fixed by the retailer. Everything between those external anchors — the windows for hindsight, concept, development, costing and review — is the business’s own, and those internal windows are the only part of the calendar that can flex when something slips.

Who owns it. In most teams the calendar is held by merchandising or by planning, sometimes by a product operations or merchandise operations role in larger businesses. What matters is that one person publishes it, owns its versions and moves a date only with a recorded reason. A calendar that every function keeps its own copy of has as many versions as there are functions, and the lock date is whichever one the person in the room remembers.

What it is not. The line planning calendar is not the whole time-and-action calendar a sourcing team keeps for each order, with its lab dips, fit approvals, pre-production samples and inspections. It is the level above: the milestones that change what the line is, and the handful of supply-chain dates that bound them. A sourcing calendar sits underneath it, and the two have to agree on the purchase order date, the production start and the ex-factory date.

The fourteen milestones, in order

Every line planning calendar, whatever its vertical, runs through roughly the same fourteen milestones. Some businesses merge two — a small brand may hold its first line review and sign its architecture in one meeting — and some add more, such as a mid-development review or a second market. The order is the part that does not change, because each milestone consumes what the one before it produced.

Season strategy and financial envelope
What it decides
What the line is for, and the sales, margin and open-to-buy it inherits
Must exist first
The merchandise financial plan for the season
What it releases
Category roles and budgets that every later count divides
Hindsight
What it decides
Which carryover earns a slot; which tiers and deliveries need more or fewer options
Must exist first
Selling and margin by option from the comparable season, however partial
What it releases
Carryover candidates and the cells to grow or shrink
Concept and trend direction
What it decides
The season’s story, themes, silhouettes, colors and materials, and how much newness it needs
Must exist first
The strategy and the hindsight
What it releases
The newness brief and early fabric and color development
Line architecture and option counts
What it decides
Option counts by category, price tier and delivery; each slot flagged carryover or new
Must exist first
The envelope, the carryover list, the newness brief and first supplier minimums
What it releases
A counted brief for development
First line review
What it decides
Whether the frame and the first concepts are the right line for the money
Must exist first
The architecture and first concepts placed against slots
What it releases
Proto requests, fit blocks and fabric development
Development and proto
What it decides
Which concepts become samples that fit, construct and read as intended
Must exist first
Tech packs, approved fabrics and trims at development stage
What it releases
Approved protos and costing requests
Costing
What it decides
Confirmed costs and supplier minimums by option
Must exist first
Approved protos and the planned quantities by option
What it releases
A margin check on real quotes, and the cells that fail it
Final line review
What it decides
Whether the line can be bought as it stands, cell by cell
Must exist first
Confirmed costs, cleared minimums and a current reserve list
What it releases
The last adds, cuts and swaps, and the list of open items
Line lock
What it decides
The option count, the flags and the price architecture, as a dated version
Must exist first
A final review with its open items closed
What it releases
Salesman samples, style master data, photography and line-sheet layout
Line sheet release
What it decides
The wholesale and retail prices, size runs, minimums and delivery windows offered to accounts
Must exist first
The locked line and confirmed prices
What it releases
Sell-in: appointments, price lists and order capture
Sales market and prebook
What it decides
What accounts book, which becomes the first demand read on the line
Must exist first
Line sheets, salesman samples and the market dates
What it releases
Bookings by option, and the options that failed to book
Buy and PO placement
What it decides
Quantities by option, size and delivery, committed on purchase orders
Must exist first
Consolidated bookings, the direct-channel plan and the open-to-buy
What it releases
Bulk fabric and trim, production slots
Production
What it decides
Nothing about the line — it executes it
Must exist first
Bulk fabric and trim at the factory, approved pre-production samples
What it releases
Finished goods, inspection and the ex-factory date
Ship
What it decides
Nothing about the line — it delivers it
Must exist first
Finished goods, booked freight and customs documentation
What it releases
Goods in the distribution centre, then on the floor

The first eight milestones are planning: they change what the line is. The ninth, the lock, is the hinge. The last five are commitment and execution: they sell, buy, make and move the line the first nine decided. A milestone in the first group that slips can be absorbed by the windows around it; a milestone in the second group that slips usually cannot, because by then the dates are held by factories, freight and accounts.

1. Season strategy and financial envelope

Decides: What the line is for, and the sales, margin and open-to-buy it inherits. Owned by: Merchandising, with planning; finance or leadership signs the envelope.

The season opens when the line is given a job and a budget. The strategy names each category’s role, the price positioning the line has to hold, the share of newness the season can carry and which deliveries carry the story; the financial envelope gives each category its sales, margin and open-to-buy from the merchandise financial plan. How the strategy and the envelope are built is set out in what is line planning; for the calendar, what matters is the date.

This is the milestone most often left without one. A season whose strategy is “being finalised” while design is already drawing has started its calendar without its first milestone, and every later review will re-argue it. Give the strategy a signing date and a signer, even if the envelope is revised later as the financial plan is re-forecast.

2. Hindsight

Decides: Which carryover earns a slot; which tiers and deliveries need more or fewer options. Owned by: Planning, with merchandising.

The hindsight reads how the comparable season sold — by option role, price tier and delivery, not just by category total — and turns it into decisions: which carryover has earned its slot, which tiers or deliveries over- or under-delivered, which tests produced a read. The method is in hindsighting the line.

On the calendar, the hindsight has a timing problem that every planner meets: the comparable season is usually still selling, or has not even reached the floor, when the hindsight for the next one is due. The worked example below shows how large that gap can be. The calendar answer is not to skip the hindsight but to schedule it in two parts — a first read at this milestone on the last full season, and a second read on the comparable season’s early selling, timed to land before the decisions it informs.

3. Concept and trend direction

Decides: The season’s story, themes, silhouettes, colors and materials, and how much newness it needs. Owned by: Design, with merchandising.

Design sets the season’s direction — themes, silhouettes, colors, materials — and merchandising tests it against what the customer will buy and against the newness share the strategy allowed. The output is a newness brief: how many new concepts the line needs, roughly where they sit, and which fabrics and colors need development started now. The bridge from direction to range is covered in from mood board to assortment and the palette in building the color story.

The calendar reason to date this milestone is fabric. Developed fabrics, custom prints and custom colors take longer to sample and longer to bulk than stock-supported ones, so a concept direction that arrives late compresses the time available to develop the very materials that make the season new. The concept window is where the season’s longest lead times begin, even though no option has been counted yet.

4. Line architecture and option counts

Decides: Option counts by category, price tier and delivery; each slot flagged carryover or new. Owned by: Planning drafts; merchandising signs.

Planning turns the strategy, the envelope, the carryover list and the newness brief into a frame of counted slots: option counts by category, price tier and delivery, each slot flagged carryover or new, each with its planned depth, target cost and margin. The step-by-step build is in how to build a line plan, the price ladder in line architecture: good, better, best and the counting unit in what counts as one option.

On the calendar, the architecture is the milestone that sizes the rest of development. The option count sets how many protos will be requested, how many costings sourcing will chase and how much sample capacity the first rounds need. An architecture signed late leaves development starting on concepts without slots, which is how a line ends up with more protos than it can carry and a final review spent cutting good product.

5. First line review

Decides: Whether the frame and the first concepts are the right line for the money. Owned by: Merchandising chairs; design, planning and sourcing attend.

The first line review walks the strategy, the frame and the first concepts placed against slots. Its question is whether this is the right line for the money before development money is spent. It is the cheapest review at which to change direction, because nothing has been sampled yet. The running order of a review is in how to run a line review and the agenda and decision log in the line review agenda template.

On the calendar, the first review is also the concept lock: it releases proto requests, fit blocks and fabric development, all of which are expensive to redirect afterwards. A first review that slips by two weeks takes two weeks out of development unless the final review moves too, and the final review is usually pinned by the lock behind it.

6. Development and proto

Decides: Which concepts become samples that fit, construct and read as intended. Owned by: Design and product development, with sourcing.

Development turns concepts into protos that fit, construct and read as intended. It usually runs in rounds — a first proto, comments, a second proto — with fittings, fabric approvals and color approvals inside each. The number of rounds is a planning assumption that varies by category: a carryover body with a new color may need none, a new tailored silhouette several.

This is the longest planning window on most calendars and the one that absorbs the most pressure. When it compresses, the usual response is to drop a proto round, which moves fit risk into production. Plan the window by category rather than as one block, so the categories with new blocks or new constructions get the rounds they need and the carryover-heavy categories release their capacity to them.

7. Costing

Decides: Confirmed costs and supplier minimums by option. Owned by: Sourcing, with planning.

Costing confirms what each option will cost at the planned quantity and what the supplier’s minimums are — per option at the factory, and per fabric and color at the mill. First-pass costs usually start alongside development; the milestone on the calendar is the date confirmed costs and minimums are in hand. How a target cost is set from a margin goal is in costing the line to a margin target.

Costing is scheduled ahead of the final review, not alongside it, because the final review is where cells that fail margin or minimum get fixed — re-costed, re-tiered, consolidated onto a shared fabric or cut. A week between confirmed costs and the review gives planning time to rerun the margin and name the failing cells before the room sits down.

8. Final line review

Decides: Whether the line can be bought as it stands, cell by cell. Owned by: Merchandising chairs; every function signs its line.

The final review asks whether the line can be bought as it stands: every cell at count, every slot flagged, every cost confirmed or explicitly open, every option above its minimum. The last adds, cuts and swaps happen here, using the reserve list, and the review ends with a short list of open items and an owner for each.

Leave a gap between the final review and the lock. Even a well-prepared final review leaves items open — a cost still being negotiated, a fabric awaiting a lab dip, a swap that needs one more fitting. A week to close them means the lock signs a line with nothing open; no gap means either the lock carries open items into the line sheet or the final review is held again.

9. Line lock

Decides: The option count, the flags and the price architecture, as a dated version. Owned by: Merchandising, as the single owner who can unlock.

The lock signs the option count in every cell, the carryover or new flag on every slot and the price architecture, as a dated version with a named owner. It is a state change rather than a meeting, and it releases downstream work: salesman samples, style master data, the photography shot list and the line-sheet layout. The full treatment, including the cost of changing a locked line, is in locking the line.

On the calendar, the lock date is set by whichever downstream constraint is tighter: the time to build and release the line sheet before market, or the time to make salesman samples before market. In the worked example below the two constraints happen to give the same date, so both have to be protected. A team that sets the lock date from the planning side — “when development is done” — finds out at market which constraint it broke.

10. Line sheet release

Decides: The wholesale and retail prices, size runs, minimums and delivery windows offered to accounts. Owned by: Wholesale or sales operations, from merchandising’s locked line.

The line sheet presents the locked line to wholesale accounts: images, style numbers, colorways, size runs, wholesale and retail prices, minimums and delivery windows. Every field is a commitment, which is why it is built from the locked line rather than from a board still in review. The difference between the internal board and the external sheet is in internal vs wholesale line sheet, and the tool category that publishes sheets in line sheet software.

On the calendar the line sheet release is also the commercial lock: prices stop being provisional. The window between the line lock and the line sheet release is where wholesale prices are derived, the margin is reread at wholesale, photography is shot and the layout is built. It is often shorter than it looks, because it tends to fall across a holiday, as it does in the example.

11. Sales market and prebook

Decides: What accounts book, which becomes the first demand read on the line. Owned by: Sales, with merchandising.

Market week is when the line is shown to accounts — at a trade show, in a showroom, in rep appointments or in a key account’s own line review — and the prebook window that follows is when accounts place their orders. Bookings are the line’s first demand read before production, and the options that fail to book become candidates to cut. See prebook.

For the calendar, market week is an external anchor: the brand rarely chooses it. That is why the backwards schedule checks it rather than derives it. If the date the supply chain implies for the market is earlier than the trade calendar allows, the window between prebook close and the buy gets shorter; if it is later, the brand shows a line it locked earlier than it needed to. A direct-to-consumer brand has no market and skips this milestone, and its first demand read comes after launch instead.

12. Buy and PO placement

Decides: Quantities by option, size and delivery, committed on purchase orders. Owned by: Planning and buying; sourcing places the orders.

The buy consolidates bookings, the direct-channel plan and the open-to-buy into quantities by option, size and delivery, and commits them on purchase orders. It is the buy lock: after it, a change is an inventory decision rather than a planning one. The window between prebook close and the buy is where bookings are read, options that failed to book are cut or kept on purpose, and size curves are applied — retail-plan.com has a size curve calculator for that last step.

The purchase order date is the hinge of the supply half of the calendar: it is the latest date at which the brand can commit quantities and still have bulk fabric and trim reach the factory in time for production. Every lead time that runs longer than the window between the PO and the production start has to be committed earlier — before the buy is final — and that is the critical path discussed below.

13. Production

Decides: Nothing about the line — it executes it. Owned by: Sourcing and production.

Production cuts, sews, finishes, inspects and packs the line. It decides nothing about the line itself, but the line planning calendar needs two of its dates: the production start, which the fabric and trim lead times count back from, and the ex-factory date, which shipping counts forward from.

Production slots are booked with factories, and a factory’s capacity is shared with its other customers. A late purchase order does not simply start production late; it may lose its slot and wait for the next one. That is why a slip upstream of the buy so often turns into a larger slip downstream of it.

14. Ship

Decides: Nothing about the line — it delivers it. Owned by: Logistics and the distribution centre.

Shipping moves finished goods from the factory to the distribution centre, through transit, port and customs, and then through receiving, processing and allocation to the floor or to the account. The calendar needs the ex-factory date, the in-distribution-centre date and the floor or ship date.

The floor date is where the backwards schedule starts, so shipping is the first lead time to subtract. Be explicit about which mode the calendar assumes: the same line can have a different calendar by ocean and by air, and a calendar that silently assumes the faster mode has hidden an expedite cost in its last line.

How to schedule the calendar backwards from the floor date

A calendar built forwards from the strategy answers the question “when could the line arrive?”. A calendar built backwards from the end date answers the question the business actually has: “what is the latest each milestone can happen, and are we already late?” The method is eight steps, each subtracting one stretch of the season.

1. Fix the end date and say what it means

Start from the one date the season cannot move: the in-store or floor date for a retail delivery, the ship date or delivery window promised to wholesale accounts, or the retail partner’s reset date. Write down which of these it is, because each one implies a different last milestone.

The end date sounds obvious and is often stated loosely. “August” is not an end date; “the first Monday the delivery is on the floor in all doors” is. For a wholesale account the date that matters is usually the start of the delivery window the brand has promised, and the goods have to ship from the brand’s distribution centre before it, not arrive in the account’s stores. For a retail partner it is the reset date on which the new items have to be on the shelf.

Each of those implies a different last milestone. A floor date includes the brand’s own distribution and allocation time; a ship window to accounts does not include the account’s; a reset date may require the goods to reach the retailer’s distribution centre weeks before the reset. Name the end date and the last milestone together.

2. Work the supply chain back to the purchase order

Subtract the downstream lead times one at a time — distribution centre to floor, transit and customs, production, and fabric and trim delivery to the factory — to find the latest date purchase orders can be placed. Every one of these durations is your own planning assumption, stated in weeks.

Work back through the supply chain one stretch at a time: distribution centre to floor, transit and customs to the distribution centre, production to ex-factory, and fabric and trim delivery to production start. The result is the latest purchase order date. State every duration in weeks and label it as your own planning assumption, because each one depends on the product, the factory, the country of origin, the shipping mode and the port.

Use the lead time the business actually achieves rather than the one quoted in a good month, and decide in advance whether the calendar carries any buffer. A buffer stated as its own line — two weeks of contingency before ex-factory, say — can be spent knowingly; a buffer hidden inside every lead time is spent silently by every function, and nobody knows how much is left.

3. Place the sell-in before the buy

If the line is sold to accounts before it is bought, put the time to consolidate bookings into a buy, the prebook window and the market week in front of the purchase order date, and check the market week against the trade calendar, which the brand rarely controls.

A wholesale-led line is sold before it is bought. Before the purchase order date, the calendar needs a window to consolidate bookings into a buy; before that, the prebook window in which accounts place orders; and before that, the market week at which the line is shown. Add them in that order, then compare the market date the arithmetic produces with the one the trade calendar or the key accounts have actually set.

If the two disagree, the external date wins, and the difference has to be absorbed by the consolidation window or by the prebook window. A direct-to-consumer line skips this step entirely, which is one reason its calendar is shorter: it buys before it sells.

4. Place the lock and the line sheet before the market

Work back from the market week to the line sheet release, and from the line sheet and the salesman-sample lead time to the line lock. The lock date is whichever of those two constraints is earlier.

Two things have to exist at market: the line sheet and the salesman samples. Work back from the market week by the time needed to finalise and release the line sheet, and separately by the time needed to produce salesman samples. Each gives a latest lock date. The lock date is the earlier of the two, and whichever one set it is the one to protect when the season is under pressure.

Between the lock and the line sheet release sit photography, wholesale pricing, the margin reread at wholesale and the layout. Between the lock and market sit sample orders, sample production and sample shipping. The two windows run in parallel, so they can be shortened only by spending money — an expedited sample, a second studio day — and that is the point at which the lock’s date stops being a planning choice.

5. Place costing and the final line review before the lock

Put the final line review a short window ahead of the lock, so open items can close, and put confirmed costs and supplier minimums ahead of the final review, so the review signs a line it knows it can buy at the planned margin.

Put the final line review a short window ahead of the lock, so its open items can close. Put confirmed costs and supplier minimums a short window ahead of the final review, so planning can rerun the margin and the minimum check and bring the failing cells to the room. That ordering is the single most protective decision on the calendar.

It also tells sourcing when its quotes are due. A costing date written on the calendar becomes a date sourcing can hold factories to; a costing that is due “before the final review” arrives the morning of it.

6. Place development and the first line review

Work back through the proto rounds to the first line review, which signs the frame development will fill. The number of proto rounds and the time each takes are the largest planning assumptions in this half of the calendar.

Work back from the costing window through the proto rounds to the first line review. The number of rounds and the time each takes — making a proto, shipping it, fitting it, commenting and remaking — are the largest assumptions in the planning half of the calendar, and they differ by category. Calendars that use one development window for every category end up too long for carryover and too short for new silhouettes.

The first line review is the concept lock, so it releases the proto requests. If the arithmetic puts the first review earlier than the architecture can realistically be ready, that is the first sign the season is late, and it is cheaper to find out here than at the final review.

7. Place strategy, hindsight, concept and architecture at the front

Work back through the line architecture, the concept and trend window, the hindsight read and the season strategy to find the date planning for the season has to start. If that date is already behind you, the season is late before it begins, and you choose now which windows compress.

Work back through the windows at the front of the season: from the first line review to the architecture, from the architecture to the concept direction, from the concept to the hindsight, and from the hindsight to the season strategy. These windows are short, but they are where the season is defined, and squeezing them saves days at the front and costs weeks of re-argument later.

The result is the date line planning for the season has to start. If that date is already behind you, the season is late before it has begun, and the honest move is to decide now which windows compress — fewer proto rounds on carryover categories, a shorter concept window, a smaller line — rather than to let each function discover its share of the delay on its own.

8. Check the calendar against the other seasons and the holidays

Lay the new calendar over the seasons already in flight and over office and factory holiday closures. Move any milestone that lands on a closure or on the same week as another season’s lock, and record the move with its reason.

A calendar is not finished when its own arithmetic works. Lay it over the seasons already in flight — the next section shows that two or three are in flight at once — and over the holiday closures of every office and factory on the critical path, including the year-end break and the Lunar New Year shutdown in many Asian sourcing countries, which falls in late January or February.

Move any milestone that lands on a closure, or in the same week as another season’s lock or final review, because the same people sit in both rooms. Record every move and its reason in the calendar’s version history, so the next season starts from the calendar that worked rather than from the one first drafted.

A dated calendar for a Fall 2028 first delivery

Every lead time below is illustrative — a planning assumption chosen so the dates can be checked, not an industry benchmark and not drawn from any brand. Your own lead times will differ by category, factory, country of origin and shipping mode; the method is what carries over.

Take a hypothetical wholesale-led apparel brand planning the first delivery of its Fall 2028 season, sourced from overseas factories and shipped by ocean. The floor date for the first delivery is Monday 7 August 2028. Every milestone in the example falls on a Monday, so each lead time is a whole number of weeks.

The supply half, worked back from the floor. Two weeks from the distribution centre to the floor puts the goods in the distribution centre on Monday 24 July 2028. Six weeks of ocean transit, port and customs put the ex-factory date on Monday 12 June 2028. Six weeks of production put the production start on Monday 1 May 2028. Eight weeks for stock-supported bulk fabric and trim to reach the factory put the purchase order date on Monday 6 March 2028 — 22 weeks before the floor.

The sell-in, worked back from the buy. Two weeks to consolidate bookings into the buy put the prebook close on Monday 21 February 2028. A four-week prebook window opens with market week on Monday 24 January 2028. The line sheet goes to accounts two weeks before market, on Monday 10 January 2028. Salesman samples take six weeks, so they have to be ordered by Monday 13 December 2027; the line sheet needs four weeks after the lock, which would also allow a lock on 13 December. Both constraints give the same date here, so the line locks on Monday 13 December 2027, 34 weeks before the floor.

The planning half, worked back from the lock. One week to close open items puts the final line review on Monday 6 December 2027. Confirmed costs and minimums are due a week earlier, on Monday 29 November 2027, after a four-week costing window that opens with proto approval on Monday 1 November 2027. Two proto rounds of four weeks each put the first line review on Monday 6 September 2027. Three weeks before that, the architecture and option counts are drafted, on Monday 16 August 2027; four weeks before that, the concept and trend direction is signed, on Monday 19 July 2027; two weeks before that, the hindsight is read, on Monday 5 July 2027; and three weeks before that, the season strategy and financial envelope are signed, on Monday 14 June 2027.

Season strategy and envelope
Date
Mon 14 Jun 2027
Weeks to floor
60
Illustrative lead to next
3 weeks to the hindsight
Hindsight
Date
Mon 5 Jul 2027
Weeks to floor
57
Illustrative lead to next
2 weeks to concept
Concept and trend direction
Date
Mon 19 Jul 2027
Weeks to floor
55
Illustrative lead to next
4 weeks to the architecture
Line architecture and option counts
Date
Mon 16 Aug 2027
Weeks to floor
51
Illustrative lead to next
3 weeks to the first review
First line review
Date
Mon 6 Sep 2027
Weeks to floor
48
Illustrative lead to next
8 weeks: two proto rounds of 4
Development and proto approval
Date
Mon 1 Nov 2027
Weeks to floor
40
Illustrative lead to next
4 weeks of costing
Costing confirmed, with minimums
Date
Mon 29 Nov 2027
Weeks to floor
36
Illustrative lead to next
1 week to the final review
Final line review
Date
Mon 6 Dec 2027
Weeks to floor
35
Illustrative lead to next
1 week to close open items
Line lock
Date
Mon 13 Dec 2027
Weeks to floor
34
Illustrative lead to next
4 weeks to the line sheet
Line sheet release
Date
Mon 10 Jan 2028
Weeks to floor
30
Illustrative lead to next
2 weeks to market
Market week opens
Date
Mon 24 Jan 2028
Weeks to floor
28
Illustrative lead to next
4-week prebook window
Prebook closes
Date
Mon 21 Feb 2028
Weeks to floor
24
Illustrative lead to next
2 weeks to consolidate the buy
Buy and PO placement
Date
Mon 6 Mar 2028
Weeks to floor
22
Illustrative lead to next
8 weeks of fabric and trim
Production start
Date
Mon 1 May 2028
Weeks to floor
14
Illustrative lead to next
6 weeks of production
Ex-factory
Date
Mon 12 Jun 2028
Weeks to floor
8
Illustrative lead to next
6 weeks of transit and customs
In the distribution centre
Date
Mon 24 Jul 2028
Weeks to floor
2
Illustrative lead to next
2 weeks to the floor
Floor date
Date
Mon 7 Aug 2028
Weeks to floor
0
Illustrative lead to next
—

Check the sum. The leads between milestones are 3 + 2 + 4 + 3 + 8 + 4 + 1 + 1 + 4 + 2 + 4 + 2 + 8 + 6 + 6 + 2 weeks, which is 60. Sixty weeks before Monday 7 August 2028 is Monday 14 June 2027, the strategy date in the table. Read down the “weeks to floor” column and every step is the lead on the row above it: 60 − 3 = 57, 57 − 2 = 55, and so on down to 2 − 2 = 0.

What the example shows. Three things stand out. First, more of the calendar lies after the lock than before it: 26 weeks from strategy to lock, 34 from lock to floor. The planning half is where the line is decided, but it is the shorter half. Second, the lock is set from the market, not from development: it is the salesman-sample lead time and the line-sheet window, counted back from 24 January, that put it on 13 December. Development has to finish in time for that date; the date does not wait for development.

Third, the calendar runs straight through two holiday periods. The four weeks between the lock on 13 December 2027 and the line sheet on 10 January 2028 include the year-end break, so the working time to photograph, price and lay out the line sheet is shorter than four weeks. And market week opens on 24 January 2028, a period when many Asian factories are preparing to close for the Lunar New Year, so salesman samples have to be finished and shipped before those closures rather than in the last days of the sample window. Step 8 exists for exactly this.

Where it would change. Air freight instead of ocean shortens the supply half and costs more per unit; a domestic or near-shore factory shortens transit and may lengthen production; a direct-to-consumer brand drops the line sheet, the market and the prebook, and can lock later and buy sooner. Each of those is a different calendar built with the same eight steps — the example is the method, not the answer.

Where the four locks sit on the calendar

Locking the line describes a range that needs four locks — concept, range, commercial and buy — each fixing one class of attribute and leaving the others open. On the calendar, each lock is a milestone that already exists, which is the easiest way to make the four locks real rather than a vocabulary.

Concept lock
Calendar milestone
First line review
Date in the example
Mon 6 Sep 2027
What it fixes
The story, the categories and the frame of counted slots
Range lock
Calendar milestone
Line lock
Date in the example
Mon 13 Dec 2027
What it fixes
The option count, the flags and the price architecture
Commercial lock
Calendar milestone
Line sheet release
Date in the example
Mon 10 Jan 2028
What it fixes
Wholesale and retail prices and the cost they rest on
Buy lock
Calendar milestone
Buy and PO placement
Date in the example
Mon 6 Mar 2028
What it fixes
Quantities by option, size and delivery

Read the dates as intervals. The concept lock on 6 September 2027 and the range lock on 13 December 2027 are 14 weeks apart: that is the time development has to fill the frame. The range lock and the commercial lock on 10 January 2028 are four weeks apart: that is the time to turn a locked line into confirmed prices. The commercial lock and the buy lock on 6 March 2028 are eight weeks apart: that is the time the line spends being sold before it is bought.

A business that runs a single sign-off has, in effect, put all four on one date — and on the calendar it is visible what that costs. Put the single sign-off at the range lock and prices are fixed four weeks before they need to be, before wholesale pricing and the margin reread at wholesale are done; put it at the buy and development works for six months against a line that can still be re-scoped.

Two or three seasons in flight at once

A season’s calendar is longer than the gap between seasons, so seasons overlap. In the illustrative calendar each season runs 60 weeks from strategy to floor, and a two-season business starts a new one every 26 weeks. Sixty divided by 26 is about 2.3, so at any date two or three seasons are in planning or production, and another is on the floor. A business with four seasons or monthly drops has more.

The table reads the same calendar for four consecutive seasons, each starting 26 weeks after the last, at five dates on the Fall 2028 clock. Week numbers are counted from each season’s own strategy date; Fall 2027’s floor is week 60 of its own calendar, and it is read here as on the floor for an illustrative 26 weeks before it closes.

14 Jun 2027 (week 0)
Fall 2027
Ex-factory (week 52)
Spring 2028
Line lock (week 26)
Fall 2028
Strategy and envelope
Spring 2029
Not started; opens in 26 weeks
6 Sep 2027 (week 12)
Fall 2027
Four weeks on the floor
Spring 2028
Buy and PO placement (week 38)
Fall 2028
First line review
Spring 2029
Not started; opens in 14 weeks
13 Dec 2027 (week 26)
Fall 2027
18 weeks on the floor
Spring 2028
Ex-factory (week 52)
Fall 2028
Line lock
Spring 2029
Strategy and envelope (week 0)
6 Mar 2028 (week 38)
Fall 2027
Closed; full hindsight
Spring 2028
Four weeks on the floor
Fall 2028
Buy and PO placement
Spring 2029
First line review (week 12)
12 Jun 2028 (week 52)
Fall 2027
Closed
Spring 2028
18 weeks on the floor
Fall 2028
Ex-factory
Spring 2029
Line lock (week 26)

The collision weeks. Look at the first row. In the week the Fall 2028 strategy is signed, Spring 2028 is locking its line and Fall 2027 is leaving the factory. The same merchandising and planning team is in all three conversations, and the strategy for one season is being written in the same week the previous season’s final open items are being closed. The third row repeats the pattern a season later: Fall 2028 locks the week Spring 2029 signs its strategy. On this calendar, every lock lands on the same week as the next season’s strategy, because the two are exactly 26 weeks apart in their own calendars.

That is a scheduling choice, not a law, and it is the kind of collision step 8 is for. Moving the strategy milestone a week or two earlier — so it is signed before the previous season’s lock week rather than in it — costs nothing on the critical path, because the front windows have room, and it gives the strategy the team’s attention.

The hindsight gap. The overlap also explains why the hindsight is always partial. Fall 2027 reaches the floor on Monday 9 August 2027, five weeks after the Fall 2028 hindsight milestone on 5 July 2027 — so when Fall 2028’s hindsight is read, the comparable season has not yet sold a unit, and the read has to rest on the last full season and on Spring 2027. Fall 2027’s first four-week read lands on Monday 6 September 2027, the week of Fall 2028’s first line review. And if Fall 2027 sells for an illustrative 26 weeks, it closes around Monday 7 February 2028, eight weeks after Fall 2028 has locked on 13 December 2027.

The calendar answer is to schedule the reads rather than wish for them: put the comparable season’s first read on the first line review’s agenda, where carryover calls are still cheap, and put a second read before the final review for the carryover options whose call depends on how they sell. The rest of the full-season hindsight goes to the season after. This is the same logic as balancing carryover and newness, applied to dates.

The critical path: what has to happen before what

Most milestones on the calendar can slip a little without moving the floor date, because the windows around them have some room. A few cannot. The critical path is the chain of dependencies whose lead times are longer than the window the calendar gives them, and on a line planning calendar it runs through three things: fabric and trim lead times, supplier minimums, and costing.

Stock-supported bulk fabric
Illustrative lead
8 weeks
Latest start
Mon 6 Mar 2028 (the PO date)
What it forces
Nothing earlier — it rides on the purchase order
Custom-dyed trim
Illustrative lead
10 weeks
Latest start
Mon 21 Feb 2028
What it forces
Ordered the day the prebook closes, before the buy is consolidated
Developed fabric
Illustrative lead
12 weeks
Latest start
Mon 7 Feb 2028
What it forces
Committed on two weeks of bookings, mid-prebook
Custom-developed fabric
Illustrative lead
20 weeks
Latest start
Mon 13 Dec 2027
What it forces
Booked on the day the line locks
Salesman samples
Illustrative lead
6 weeks
Latest start
Mon 13 Dec 2027
What it forces
Ordered at the lock to arrive for market on 24 Jan 2028
Supplier minimums
Illustrative lead
With costing
Latest start
Mon 1 Nov 2027 (due 29 Nov 2027)
What it forces
Confirmed before the final review can test each option
Confirmed costs
Illustrative lead
4 weeks
Latest start
Mon 1 Nov 2027 (due 29 Nov 2027)
What it forces
In hand a week before the final review reruns margin

Fabric and trim lead times

The calendar gives fabric and trim eight weeks, from the purchase order on 6 March 2028 to the production start on 1 May 2028. A stock-supported fabric that the mill can deliver in eight weeks fits that window and can ride on the purchase order. Anything longer has to be committed before the buy is final.

Count back from 1 May 2028. A custom-dyed trim with an illustrative 10-week lead has to be ordered by 21 February 2028 — the day the prebook closes, before bookings have been consolidated into a buy. A developed fabric with an illustrative 12-week lead has to be committed by 7 February 2028, two weeks into the prebook window, on partial bookings. A custom-developed fabric with an illustrative 20-week lead has to be booked by 13 December 2027 — the day the line locks. For that fabric, the choice of material is final at the lock, and the quantity is committed months before anyone has booked it.

There are three ways to live with that, and a calendar should say which one each long-lead material uses. Commit the fabric at risk on the planned quantity and accept the exposure; reserve greige or mill capacity early and commit the color or finish later; or platform the fabric across several options so that a booking for one fabric is spread across many, which lowers the risk that any one option’s booking is wrong. See fabric platforming.

What the calendar should not do is give every material the same lead and discover the long ones at the buy. Ask sourcing for the lead time of every fabric and trim that has to be developed, at the concept milestone, and put each one that exceeds the PO-to-production window on the calendar as its own dated milestone.

Minimums confirmed before the lock

Supplier minimums — per option at the factory, per fabric and color at the mill — put a floor under depth and so a ceiling on the option count. A line locked before minimums are confirmed can lock options that cannot be made at the planned quantity at quoted cost, and the problem surfaces at the buy, when the only fixes are a surcharge, a consolidation onto a shared fabric or a cut after the line sheet has gone out.

On the calendar, minimums are confirmed with costing, by 29 November 2027 in the example, so the final review a week later can check every option against its minimum and fix the failures while the line can still change by swap. The arithmetic of a minimum against an option count is in what is line planning.

Costing before the final review

The final review asks whether the line can be bought at the planned margin, and it can only answer that on confirmed costs. If costs arrive after the review, the review signs counts on target costs, and every cost that comes in above target turns into a post-lock change: re-tier, re-engineer, cut or accept the lower margin.

So the calendar puts confirmed costs a week ahead of the final review, with the date written down and owned by sourcing. Where some costs cannot be confirmed in time — a factory still quoting, a new construction still being engineered — the calendar should say so, and the final review should carry those options as explicitly open rather than as costed.

One calendar per delivery: drops and channels

The example is the calendar for one delivery. A season with several deliveries has several end dates, and the supply half of the calendar is worked back separately from each one, while the planning half is usually shared. How many deliveries a season should have, and what each carries, is set out in planning drops on the line board.

Take a second Fall 2028 delivery on the floor four weeks after the first, on Monday 4 September 2028. Worked back alone with the same illustrative leads, its purchase orders could wait until Monday 3 April 2028, four weeks after the first delivery’s, and its lock could wait until Monday 10 January 2028.

Wholesale-led: one market, one lock. If both deliveries are shown at the same market week, the second delivery cannot lock in January — it has to be on the line sheet that goes out on 10 January, and its salesman samples have to be at market on 24 January. So it locks with the first delivery on 13 December 2027, 38 weeks before its own floor date rather than 34. What the second delivery gains is not a later lock but a later buy: four more weeks of booking data before its purchase orders are placed on 3 April.

Direct-to-consumer-led: a lock per drop. Without a market, each drop can lock on its own calendar, as late as its supply half allows. The second drop in the example could lock on 10 January 2028 and use four more weeks of development — or of reading how the comparable drop sold. This is one of the real advantages of a direct-to-consumer calendar: later drops in the season can respond to earlier ones.

Both at once. A brand that sells the same line wholesale and direct runs the wholesale calendar for the line and can hold direct-only options or colors to a later lock, as long as they are flagged as their own cells. The risk is the reverse: a direct-only addition made after the wholesale lock that quietly uses fabric or factory capacity the wholesale buy was counting on.

How the calendar differs by vertical

The fourteen milestones hold in every vertical. What changes is the date the calendar is worked back from, and the lead time that sets the critical path. Each vertical below is described in its own terms; the durations are left out on purpose, because they vary too much by business to be useful as numbers.

Apparel
Worked back from
Each delivery’s floor date
Longest lead
Developed fabric and custom trim
What moves earlier
Fabric commitments ahead of the final buy
Footwear
Worked back from
Model-year launch or the prebook ship window
Longest lead
New lasts, molds and outsole tooling
What moves earlier
New bottoms decided a season or more ahead
Beauty
Worked back from
The retail partner’s reset date
Longest lead
Formula, stability testing and packaging components
What moves earlier
Shade range fixed before retailer item set-up
Home and furniture
Worked back from
The floor set or the container arrival
Longest lead
Production plus ocean freight on long-lead SKUs
What moves earlier
The line locked before the dealer market
Toys
Worked back from
The retailer’s set ahead of the gifting peak
Longest lead
Tooling and safety testing
What moves earlier
The line shown to buyers long before the peak
Outdoor and sporting goods
Worked back from
The start of the sport’s season
Longest lead
Technical fabrics and components
What moves earlier
The line locked for the prebook window

The question is the same everywhere: what is the date that cannot move, and which lead time is longer than the window the calendar gives it? The per-vertical definitions of one option, which change what the lock signs, are on how to build a line plan.

Where line planning calendars fail

Three failures recur, and each is a mechanism rather than a lapse — it happens to careful teams, because each decision that causes it is reasonable on the day it is made. All three are visible on the calendar weeks before they are visible in the season.

The lock date moves, but the ship date does not

Development runs late, a review is rescheduled, a key concept needs another fitting, and the lock moves two weeks. The floor date does not move, because it has been promised to stores and accounts, and the production and shipping windows behind it are held by factories and freight. So the slip lands entirely on the windows after the lock, which are the ones least able to absorb it.

On the example’s dates: the lock slips from 13 December to 27 December 2027. Market week still opens on 24 January 2028, so salesman samples now have four weeks, not six — ordered on the planned six-week lead they would arrive on 7 February, two weeks into a four-week prebook window. The line sheet is still due on 10 January, two weeks after the slipped lock instead of four, and those two weeks are the year-end holiday. And the custom-developed fabric with a 20-week lead still has to be booked on 13 December to make production on 1 May, so it is booked on a line that is not yet locked.

Each of the outcomes has a cost: samples are expedited, the line sheet goes out late or incomplete, or it goes out before the line is locked, and the fabric is committed at risk. The counter is to treat the lock as the calendar’s fixed point in the planning half. When development runs late, the question at the rescheduled review is not “when can we lock?” but “what do we lock on the original date, and what do we hold open?” — locking the options that are ready and carrying the rest as named open items with their own late date, as locking the line describes for post-lock changes.

Reviews scheduled before costing

Review dates are set early in the season, often by the availability of the people who have to attend, and costing is scheduled afterwards by working forwards from development. The result is a final review that falls before confirmed costs arrive. The review then signs counts on target costs, and the cost check happens after the lock.

An illustrative case: a Better option planned at $75 retail and a $30 target cost, a 60% initial markup, comes back quoted at $33 the week after the final review. Its markup falls to ($75 − $33) ÷ $75 = 56%. At the review, that option could have been re-tiered, re-engineered or swapped for a reserve concept in the same cell. After the lock, each of those is a post-lock change with downstream work already started, and the most likely outcome is that the lower margin is simply accepted.

The counter is to schedule backwards: the final review date is fixed from the lock, and the costing date is fixed from the final review, with a gap between them. If sourcing cannot confirm costs by that date, the calendar is wrong, not the review — move the costing window earlier, or plan the final review with the uncosted options explicitly open.

Line sheets released before the line is locked

Market dates do not move, so when the lock slips the line sheet is often released anyway, from a line that is still changing. Suppose the lock slips to Monday 17 January 2028 while the line sheet goes out on its planned date of 10 January. For the week in between, every change to the line is a correction to a document accounts are already reading, one week before market. Corrections that arrive after an account has planned its buy around the first version are the ones that damage the relationship.

The counter is to release a line sheet only from a locked version, and when the lock and the line sheet cannot both make their dates, to release a partial line sheet of the locked options and add the rest as a dated supplement. A smaller line sheet that is right is better than a complete one that changes. The internal and external documents are told apart in internal vs wholesale line sheet.

Five more show up often enough to name:

Keeping a calendar people plan their weeks from

A calendar is only useful if every function plans its own work from the same version. Seven columns turn a list of dates into a calendar that can be run: the milestone, its planned and actual date, its distance to the floor, its input deadline, its owner, what it releases and the calendar version it belongs to.

Milestone
What it holds
The named event, from the fourteen in order
Why it is there
A milestone without a name is a meeting nobody prepared for
Date
What it holds
The planned date, and the actual date once it happens
Why it is there
Slips are invisible if only one date is kept
Weeks to floor
What it holds
The distance to the end date
Why it is there
Shows how much room is left without date arithmetic
Input deadline
What it holds
When the milestone’s inputs are due, usually a week before
Why it is there
A review is only as current as its prework
Owner
What it holds
The one name accountable for the milestone happening
Why it is there
Shared milestones slip by consensus
Releases
What it holds
What starts downstream when the milestone is met
Why it is there
Downstream teams plan their own weeks from it
Version
What it holds
The calendar version the date belongs to
Why it is there
Two copies of the calendar are worse than none

In a small team. A small brand often runs the whole calendar through two or three people, and the risk is not complexity but the absence of anyone whose job is to say a date has passed. The same discipline applies at a smaller scale: an end date, a lock date worked back from it, a costing date before the final review, and a written record of every move. A calendar on one page that is read every week is enough.

On files or on a platform. A line planning calendar can be run on a shared spreadsheet; every date on this page is spreadsheet arithmetic. The difficulty is the same one that affects the line plan and the board: the calendar, the plan and the board are three records, and a lock that moves on one and not the others is how they start to disagree. The line plan workbook holds the counts the calendar’s milestones sign, and visual line planning software sets out what separates a board tied to the plan from a picture of it.

Ten questions to ask before the calendar goes out

A calendar is ready to publish when every one of these has an answer that the person who owns the milestone is willing to sign. A question nobody can answer is a date the season will discover on its own.

  1. Is the end date stated precisely — floor, ship window or reset — and is the last milestone named with it?
  2. Is every lead time stated in weeks, labelled as the team’s own assumption, and based on what the business actually achieves?
  3. Is the market week taken from the trade calendar or the key accounts, rather than derived?
  4. Is the lock date set by the tighter of the line-sheet window and the salesman-sample lead time?
  5. Are confirmed costs and supplier minimums due before the final review, with a gap between them?
  6. Is every fabric and trim whose lead exceeds the PO-to-production window on the calendar as its own dated milestone?
  7. Does each review have an input deadline and an owner for it?
  8. Has the calendar been laid over the other seasons in flight, and are any locks or final reviews in the same week as another season’s?
  9. Have office and factory holiday closures been checked against every milestone on the critical path?
  10. Who owns the calendar, which version is this, and where are the planned and actual dates kept?

The line board checklist covers the other half of readiness — whether the board itself is ready for the review the calendar has scheduled.

See the Platform →

Frequently asked questions

What is a line planning calendar?
A line planning calendar is the sequence of dated milestones that takes a season’s line from strategy to a locked line and a released line sheet, and on through the buy, production and shipping, worked backwards from the date the product has to be in store or ship. It turns the line planning process into dates: when the strategy is signed, when each line review happens, when the line locks, when the line sheet goes to accounts and when purchase orders are placed.
What are the milestones in a line planning calendar, in order?
Fourteen, in order: season strategy and financial envelope, hindsight, concept and trend direction, line architecture and option counts, first line review, development and proto, costing, final line review, line lock, line sheet release, sales market and prebook, buy and PO placement, production, and ship. Brands that do not sell wholesale skip the line sheet and the market, and brands with several deliveries run the later milestones once per delivery.
How far ahead of the floor date does line planning start?
It depends on the vertical, the sourcing model and the channel, so work it out from your own lead times. In the illustrative wholesale apparel calendar on this page, the season strategy is signed 60 weeks before the floor date, the line locks 34 weeks before it and purchase orders are placed 22 weeks before it. Those durations are planning assumptions chosen for the example, not industry benchmarks.
Why is a line planning calendar worked backwards?
Because the end date is the one that cannot move: the floor date, the ship window promised to accounts or the retail partner’s reset. Working forward from the strategy produces the date the line could arrive, which is usually later than the date it has to. Working backwards from the end date produces the latest date each milestone can happen, and shows at once whether the season is already late.
How many seasons are in flight at once?
Usually two or three, plus one on the floor. In the illustrative calendar each season runs 60 weeks from strategy to floor and seasons start 26 weeks apart, so 60 ÷ 26 is about 2.3. In the week the Fall 2028 strategy is signed, Spring 2028 is locking its line and Fall 2027 is leaving the factory, and the same people work on all three.
What has to be finished before the line locks?
Three things: confirmed costs, so the final line review reruns the margin on real quotes rather than targets; supplier minimums confirmed per option, so no option is locked below the quantity a factory or mill will make; and the long-lead fabrics and trims identified, because some of them have to be booked on or before the lock date. In the illustrative calendar a 20-week custom-developed fabric has to be booked on 13 December 2027, the day the line locks.
What happens when the line lock slips but the ship date does not?
The slip lands on the windows after the lock, because production and shipping are already fixed by the floor date. In the illustrative calendar, a two-week slip from 13 December to 27 December 2027 leaves four weeks, not six, for salesman samples before market week opens on 24 January 2028, and two weeks, not four, to build a line sheet that is still due on 10 January. Sampling is expedited, the line sheet goes out late, or it goes out before the line is locked.
How does the line planning calendar differ by vertical?
The milestones hold, but the end date and the longest lead change. Apparel works back from each delivery’s floor date; footwear runs new lasts, molds and outsole tooling on an earlier track inside a model-year calendar; beauty works back from the retail partner’s reset date and shade launches; home and furniture lock before the dealer market because production and ocean freight on long-lead SKUs fix the buy months ahead; toys are shown to buyers long before the gifting peak; and outdoor and sporting goods lock for the prebook window of each sport’s season.

See how a line board works when it is connected to the plan. Canvas — the visual line board inside RetailNorthstar — links the board to open-to-buy, the assortment, sizing, purchase orders, and production, so the board stays live instead of going stale.